Cleaning:
Cracks are cleaned of all dirt, sand and debris using no less than a 185 cfm compressor at 110 psi.
This will facilitate adhesion of rubberized material to the asphalt. All vegetation must be
removed prior to application of material. It is recommended that a weed steril and be applied one
week before removal to prevent vegetation re-growth.
Heat Lance:
All moisture must be removed from cracks to allow proper adhesion of rubberized material. A
specialized hot air head lance is required for this purpose. The heat lance accompanied by a
185 cfm compressor produces an air stream velocity of 3,000 ft/sec. and an air temperature
of 33,000 degrees fahrenheit.
Grinding:
Grinding provides for better adhesion of rubberized material to the asphalt crack's side wall.
It also creates a reservoir for rubberized sealants. This reservoir of material will last longer
and make for a better quality seal. Cracks 1/8" to 3/8" should be ground to a minimum of 1/2" wide
by 1/2" deep.
Material Application:
RW rubberized sealants should be applied in prepared cracks at a temperature of approximately 380
degrees Fahrenheit.
|